October 24, 2011 - 4:28pm
2 years 39 weeks ago

The past few months have been frustrating for drivers who rely on Maple Avenue in Zanesville, but that's all about to change.

The construction project is almost finished, and crews are expected to clean up next week.  Deputy Director for the Ohio Department of Transportation District 5 Joe Rutherford said the manhole covers will be smoothed out soon.

"There's actually a lot of stuff that comes up to the surface in the roadway, and we want to make sure that it's flushed...

September 19, 2011 - 5:18pm
2 years 44 weeks ago

It's time for drivers to plan alternate routes and avoid Maple Avenue in Zanesville.

Public service director Mike Sims said crews milled out side streets, and they've started working on the inside lanes of Maple Avenue.  Although progress is being made, Sims said the project might not be finished on time.

"They were supposed to be here in early to mid August, so I think they're a little behind schedule," said Sims.  "They were originally projected to...

September 6, 2011 - 1:31pm
2 years 45 weeks ago

You might not have seen any construction on State Route 60 in Muskingum County over the holiday weekend, but the project will resume next week.

Ohio Department of Transportation District 5 Deputy Director Joe Rutherford said contractors will begin working on side streets that intersect the roadway on Monday.  He said resurfacing of Maple Avenue should start on September 19th and finish by October 31st.

"Asphalt resurfacing is a weather sensitive activity, so we'll see...